An interior fit-out programme with 10 phases and 32 activities, with typical durations and the links between them. Pick a start date and download it as an Excel file.
Dates are calendar days counted from this date, so weekends and holidays are not skipped. Adjust working days after import.
10 phases, 32 activities and 48 finish-to-start links. Phases overlap where the work does.
Design & Authority Approvals
3 activities - Jan 4, 2027 to Feb 21, 2027
Procurement & Long-Lead Items
4 activities - Jan 18, 2027 to Mar 28, 2027
Demolition & Strip-out
2 activities - Feb 22, 2027 to Mar 3, 2027
MEP First Fix
4 activities - Mar 4, 2027 to Mar 17, 2027
Partitions, Ceilings & Substrates
3 activities - Mar 14, 2027 to Mar 31, 2027
Finishes & Joinery
4 activities - Apr 1, 2027 to Apr 28, 2027
MEP Second Fix & Commissioning
4 activities - Apr 15, 2027 to Apr 28, 2027
FF&E Installation & Styling
2 activities - Apr 29, 2027 to May 10, 2027
Snagging & Authority Inspections
3 activities - Apr 29, 2027 to May 18, 2027
Handover & Closeout
3 activities - May 16, 2027 to May 27, 2027
The file has these columns plus a Notes column listing typical deliverables for each activity.
| Milestone | Task name | ID | Start date | End date | Duration (days) | Predecessor |
|---|---|---|---|---|---|---|
| Design & Authority Approvals | Design Development & Material Boards | A1 | 2027-01-04 | 2027-01-17 | 14 | |
| Design & Authority Approvals | Shop Drawings & Coordination | A2 | 2027-01-18 | 2027-01-31 | 14 | A1 |
| Design & Authority Approvals | Authority & Landlord NOCs | A3 | 2027-02-01 | 2027-02-21 | 21 | A2 |
| Procurement & Long-Lead Items | Long-Lead Joinery & Millwork | A4 | 2027-02-01 | 2027-03-28 | 56 | A2 |
| Procurement & Long-Lead Items | Stone, Tiles & Hard Finishes | A5 | 2027-01-18 | 2027-02-28 | 42 | A1 |
| Procurement & Long-Lead Items | FF&E (Furniture, Fixtures & Equipment) | A6 | 2027-01-18 | 2027-03-07 | 49 | A1 |
| Procurement & Long-Lead Items | MEP Equipment Procurement | A7 | 2027-02-01 | 2027-02-28 | 28 | A2 |
| Demolition & Strip-out | Demolition Works | A8 | 2027-02-25 | 2027-03-03 | 7 | A9 |
Sign up free. No credit card needed.
Create a project. The Free plan includes one.
In the project, open the AI Drafts tab.
Click Import schedule and upload the file. The columns map automatically: Milestone, Task name, ID, Start date, End date, Duration (days), Predecessor, Notes.
Check the mapping, click Continue, look over the preview and click Import.
Review the draft plan and click Accept Draft. The phases become milestones and the activities become tasks, with their dates and links.
Ready to run it as a live schedule?
Plan it in Milesto, freeMost interior fit-outs follow the same order of work. This template starts at Design & Authority Approvals and ends at Handover & Closeout, with 32 activities in between. Starting from a realistic sequence means you adjust durations and links for your job instead of building the programme from a blank sheet.
Each activity has a typical duration in calendar days and finish-to-start links to the activities that must finish before it. Starting from the date you pick, every activity is scheduled as early as its links allow: it starts the day after the last of its predecessors ends. With these durations the whole programme runs 144 calendar days.
Long-lead procurement such as joinery, stone and furniture runs alongside approvals and site works, and the installation it feeds waits for it.
The durations are typical starting points, not a promise for any particular job. Edit task names, dates and links in the spreadsheet before you import it, or change them in Milesto afterwards. Keep the column headers as they are and one row per activity, so the import maps everything automatically.
Dates are calendar days, so weekends and holidays are not skipped. Adjust for your working days after import.
One sheet with a header row and one row per activity. The Start date and End date columns are real Excel dates, the Predecessor column lists the IDs of the activities that must finish first, and the Notes column lists typical deliverables for each activity. It opens in Excel and other spreadsheet apps that read .xlsx files.
Import the template, then track progress, the critical path and earned value as the job moves. Start on the Free plan, no credit card needed.